Thursday, April 18, 2013

UK Regulator Gives OK to Total on North Sea Elgin Restart

LONDON - The regulator of the U.K.'s offshore oil and gas industry said Wednesday that it has accepted the safety case submitted by French oil company Total SA for the restart of the Elgin gas field in the North Sea, which was shut down because of a gas leak a year ago.

"It will now be for Total to decide when to restart operations," said the U.K. Health and Safety Executive in an emailed statement.

The HSE said it is still investigating the incident on March 25 last year, but that it was satisfied that Total has, "re-evaluated the risks associated with operating the installation."

The timing of the restart of production at the Eglin-Franklin facilities, which contributed around 9% of the U.K.'s oil and gas production before the shutdown, is important for the U.K. economy as it teeters on the brink of its third recession in five years.

Copyright (c) 2012 Dow Jones & Company, Inc.

Generated by readers, the comments included herein do not reflect the views and opinions of Rigzone. All comments are subject to editorial review. Off-topic, inappropriate or insulting comments will be removed.

View the original article here

Wednesday, April 17, 2013

Total Expects to Restart Elgin within a 'Very Few Days'

Total Expects to Restart Elgin within a 'Very Few Days'

Total expects to restart production from the Elgin and Franklin fields in the North Sea within "a very few days" after the UK's Health and Safety Executive (HSE) announced Wednesday this week that it had given the go ahead for production to resume on the company's Elgin platform. The Elgin platform was shut down almost a year ago, on March 25, 2012, after a major gas leak.

A spokesman for Total told Rigzone following the HSE announcement:

"Now that the HSE has accepted the safety case we will be looking to restart safe production at Elgin as soon as it's practical to do so, which we hope will be within a very few days."

The spokesman added that Total would make an announcement once production has resumed.

The resumption of gas production at Elgin is much needed by the UK's energy infrastructure at the moment. UK energy regulator Ofgem warned Feb. 19 that a dwindling of foreign gas supplies was among the factors contributing to "uncomfortably tight" energy reserves in the country.

At the time of the leak incident in March last year, the Elgin and Franklin fields were producing around 9 percent of total UK gas production. At their peak the two fields can produce up to 280,000 barrels of oil equivalent per day (boepd), according to Total.

Once resumption begins Elgin/Franklin will reach 70,000 boepd – only half its pre-shutdown output of 140,000 boepd – by the end of this year and that it will not reach its full output until 2015, warned Patrice de Vivies, Total's senior vice president of exploration and production for Northern Europe, in February.

The restart of production should also eventually see the full complement of more than 230 personnel who work on the platform return to duty.

Total had hoped that production on the Elgin platform would resume by the end of 2012, but the HSE took longer than expected to decide if it was safe to resume production. Indeed, there was concern that the resumption of production might be delayed further when an HSE spokesman said March 1 that the safety regulator was still assessing the case for the Elgin restart and that the matter was "complex".

Total shut down and evacuated non-essential personnel from the Elgin March 25, 2012 after a sheen of gas was reported within the vicinity of the platform.

The firm soon performed a "dynamic kill" well-intervention operation – using the West Phoenix (UDW semisub) rig – that involved pumping heavy mud into the well that had leaked, which was achieved in May. A lengthier process to seal the well with cement was completed in autumn.

Total stated in August last year that the overall environmental impact of the gas leak incident at Elgin was "minimal", with 3,096 tons of natural gas and 3,076 tons of condensate being lost because of the leak. Most of this evaporated in the atmosphere, the firm said, while the sheen – representing some 407 tons of condensate – dispersed naturally into the sea.

A former engineer, Jon is an award-winning editor who has covered the technology, engineering and energy sectors since the mid-1990s. Email Jon at jmainwaring@rigzone.com.

Generated by readers, the comments included herein do not reflect the views and opinions of Rigzone. All comments are subject to editorial review. Off-topic, inappropriate or insulting comments will be removed.
For More Information on the Offshore Rig Fleet:
RigLogix can provide the information that you need about the offshore rig fleet, whether you need utilization and industry trends or detailed reports on future rig contracts. Subscribing to RigLogix will allow you to access dozens of prebuilt reports and build your own custom reports using hundreds of available data columns. For more information about a RigLogix subscription, visit http://www.riglogix.com/.

View the original article here

Saturday, April 13, 2013

UK HSE Still Assessing Case for Elgin Restart

LONDON - U.K. offshore regulator the Health and Safety Executive said Friday that it is still assessing proposals submitted by French oil company Total SA for the restart of the Elgin gas field and could not give a date for when approval might be given.

Total submitted its plans to the HSE in the last week of November to restart Elgin, which was shut down last year due to a gas leak. Typically the HSE makes a decision within 90 days, a time frame that lapsed at the end of February.

A spokesman for the HSE said it is still assessing the safety case for the Elgin restart and that the matter is complex.

The timing of the restart of production at the Eglin-Franklin facilities, which contributed around 9% of the U.K.'s oil and gas production before the shutdown, is important for the U.K. economy as it teeters on the brink of its third recession in five years.