Sunday, March 3, 2013

Report: 47 Tcf Gas Potential at Buru's Canning Permits

Buru Energy revealed Friday that RISC, an independent evaluation group, has completed an assessment of the prospective resources for all of the company's onshore permit areas in the Canning Superbasin.

The evaluation report confirmed that the Basin Centred Gas System in the Laurel Formation, spanning around 6,708 square miles (17,373 square kilometers), contains an unrisked gross recoverable volume of 47 trillion cubic feet of gas and 1,177 million barrels of condensate.

RISC has only considered the reservoirs in the overpressured part of the Laurel Formation in their analysis, Buru noted in a statement.

More work is required to quantify the resources in the extensive overlyinggas accumulation in the normally pressured section, generally above 8,202 feet (2,500 meters), Buru added.

RISC also stated its view that the existing analysis identified reservoirs which are a combination of conventional and unconventional reservoirs; the latter will likely to require stimulation.

Buru, in a joint agreement with Mitsubishi Corp, owns five permits that lie on the onshore Canning Superbasin. In November last year, the company signed an agreement with Western Australia's state government for EP 71, 391, 428, 431 and 436. The contract runs for 25 years, and comes with a separate 25-year extension option.

Buru said in November last year that the agreement provides a framework for the development of a project to deliver gas to a liquefied natural gas facility in the Pilbara, once sufficient gas has been identified to sustain domestic consumption. The JV is required to submit a proposal for the development of a domestic gas project and pipeline by June 30, 2016.

Quintella has reported on the upstream and downstream oil and petrochemicals markets from 2004. Email Quintella at quintella.koh@rigzone.com.

Generated by readers, the comments included herein do not reflect the views and opinions of Rigzone. All comments are subject to editorial review. Off-topic, inappropriate or insulting comments will be removed.

View the original article here

Trapoil Buys 33.33% of Trent East Terrace Area

UK North Sea-focused junior Trapoil announced Friday that it has agreed to buy one-third of the Trent East Terrace (TET) Area license in the southern North Sea from Perenco UK.

In return for its 33.33-percent share in Block 43.24a, where the TET Area is located, Trapoil has committed to securing a drilling rig within six months for a planned appraisal well. Trapoil’s share of the drilling costs is expected to be approximately $8 million.

It is also intended that Trapoil will be the operator of the TET Area, subject to approval from the Department of Energy and Climate Change.

TET has proven gas in the Carboniferous Westphalian and Namurian reservoirs, with gross recoverable gas resources estimated by Trapoil's management to be between 35 and 60 billion cubic feet. Trapoil's management believes that the proposed drilling of a new appraisal well could potentially recover closer to 60 bcf if all of the main porous gas-bearing sands flow at commercial rates. The existing 43/25-3 discovery well drilled by Arco British Limited flow tested from two of the five potential sands at an aggregate rate of 50 million cubic feet of gas per day.

Trapoil CEO Mark Groves Gidney commented in a company statement:

"The farm-in to the TET asset enables the group to secure operatorship, subject to DECC's approval, and therefore exercise greater control over the scheduling of our work program. In addition, this relatively straight forward gas development project, in conjunction with the promising exploration potential in the adjacent acreage, offers the prospect of attractive cash flow for the group in the medium term."

Generated by readers, the comments included herein do not reflect the views and opinions of Rigzone. All comments are subject to editorial review. Off-topic, inappropriate or insulting comments will be removed.

View the original article here

DOI Calls for Drillers to Inspect, Replace Bolts after Defects Found

The U.S. Department of the Interior (DOI) has directed U.S. Gulf of Mexico drilling operators whose rigs have a lower mariner riser package (LMRP) H4 connector manufactured by GE Oil & Gas' Hydril division to cease operations and to inspect and possibly replace these bolts after defects were uncovered on some rigs.

GE Oil & Gas issued a notice Jan. 29 to customers calling for them to inspect and remove the bolts after the upper and lower bodies of a H4 Connector contained in the LMRP of a rig operating in the U.S. Gulf of Mexico separated.

A recent investigation indicated that stress corrosion cracking caused by hydrogen embrittlement contributed to the separation of the upper and lower bodies of the LMRP, according to a GE statement.

GE is conducting a root cause analysis into the incident. Additionally, the company has been recently made aware of two additional data points found during surface inspections of the identified bolts. Both instances are being investigated.

The company has expanded the safety notice to include all H4 Connector bolts (P/N H10004-2) produced from June 2007 to October 2009 in the H4 product family, including E, DxE, ExF, HD and DWHD.

While GE is investigating the production history of these H4 Connector bolts, a preliminary investigation has indicated bolts produced during this time are more susceptible to hydrogen embrittlement.

The safety notice does not affect the SHD Connector, GE commented.

The faulty bolts should concern mainly older rigs, DOI commented.

"Operators are currently evaluating which rigs have the faulty equipment, but at this time it looks like this will have a minimum impact on the drillers as this equipment is produced over a short period of time," DOI added in a statement.

Recently delivered rigs with the Hydrill blowout preventer (BOP) that have a Super HDH-4 connector were mostly delivered after 2009, and DOI has no indication that these rigs would be affected.

Officials with DOI's Bureau of Safety and Environmental Enforcement met with industry officials late last month to discuss the initial finding associated with a pollution incident involving the discharge of a synthetic base mud in the Gulf due to a loss of integrity of a LMRP H-4 connector. During the meeting, it was introduced that zinc electroplating without proper baking, as per ASTM B633, was a possible cause of hydrogen embrittlement. BSEE was also informed during this meeting of two other rigs as having H-4 connector bolt failures.

On Jan. 25, BSEE received information from GE which identified rigs as having BOP stack connectors that may contain bolts that may no longer be fit for purpose. BSEE then contacted operators associated with this subset of rigs currently operating in the U.S. Gulf of Mexico, asking them to halt operations until the existing bolts on the LMRP connector/wellhead connector could be changed out with bolts that have been certified by an independent third-party to comply with recommended heat treatment practices or if existing bolts have been examined and certified as fit for purpose.

Though the notice covers the entire Outer Continental Shelf, the issue is only for subsea BOPs, which are typically used for floating rigs, according to a Feb. 2 research note from Barclays Capital. GE holds approximately 50 percent market share for the deepwater Gulf BOP market.

Industry sources indicate that 159 connectors from GE's Vetco division have issues. Drilling contractor Transocean Ltd. is estimated to have 60 rigs and Diamond Offshore Drilling, Inc. has approximately 30 rigs. Rigs belonging to Noble Drilling and Ensco plc are believed to be impacted, while three Seadrill rigs were affected.

While U.S. Gulf rig operators will have to stop operations to pull the BOP and fix the problem, it is believed that drilling operators operating worldwide – at least in Brazil – the bolts will be repaired the next time the BOP is pulled for a normal reason such as a new well.

For rigs operating in the U.S. Gulf of Mexico, it is not known how this will play out in terms of rigs being on day rate or not when the bolts are fixed. According to one drilling contractor, one day per BOP in time of fixing the bolts, excluding pulling and setting the BOP, could total two weeks.

A final issue is whether the rig owners have spare bolts or not, but industry analysts believe most do. GE said in its notice it would supply new bolts as appropriate. GE estimates that 9,000 to 10,000 bolts need to be replaced and has been producing replacement bolts since Feb. 2 at a rate of 500 per day, according to Barclays' analyst James C. West.

GE said in its notice it would supply new bolts as appropriate.

Halting operations to inspect and replace bolts will pose additional downtime risk for offshore drillers, but Barclays Capital analyst James C. West commented that downtime could be limited and can be often mitigated through the course of normal operations.

While the BSEE notice called for operators to halt operations until the existing bolts are replaced and verified, the notice also recommended operators consult with contractors to determine the appropriate…corrective actions," potentially leaving some room to inspect BOPs during the normal course of operations rather than stopping work immediately, said West in the Feb. 7 note.

"While we await further clarity, we think this event could present knee-jerk headline risk for some offshore drillers, particularly those with direct exposure to GE bolts," West commented.

The H4 family of subsea connectors was introduced in 1964 and is used in every major producing region worldwide and every type of offshore environment, according to Hydril's website.

Karen Boman has more than 10 years of experience covering the upstream oil and gas sector. Email Karen at kboman@rigzone.com.

Generated by readers, the comments included herein do not reflect the views and opinions of Rigzone. All comments are subject to editorial review. Off-topic, inappropriate or insulting comments will be removed.

View the original article here

Senecio Tight Gas Feasibility Study Underway

AWE disclosed Thursday that it has started on a development feasibility study for the commercialization of the onshore Senecio tight gas accumulation. The Senecio discovery is located in the north Perth Basin, Western Australia.

Analysis of pressure tests conducted in November 2012 and other data captured since the fracture stimulation has confirmed permeability of between 0.03 millidarcy (mD) to 0.06 mD, which is within the pre-fracture estimated range.

"This analysis, together with the successful flow test in September 2012 that reported a stabilized gas rate of 1.35 million standard cubic feet of gas per day, with a 16-foot (five-meter) perforation interval, demonstrates potentially commercial reservoir flow capacity," AWE said in a statement. AWE's project partner is Origin Energy. Both of the companies have an equal stake in the partnership.

AWE has previously booked a 2C contingent resource for its 50 percent equity share of Senecio of 4.4 million barrels of oil equivalent (mmboe). Previously interpreted 2D seismic data indicated a potential estimated recoverable volume of at least double the quantity currently booked. An outcome of the feasibility study will be an updated definitive resource estimate which will be based on latest interpretation of the well data, the new 3D seismic data, and planned reservoir modeling studies.

AWE's Managing Director Bruce Clement, said that the Senecio tight gas commercialization program is gaining momentum and that positive subsurface data has given the company considerable confidence that commercial gas production can be achieved from the Senecio discovery.

"The results of the pressure test, the flow test, and the Irwin 3D seismic program indicate that a horizontal, multi-stage, hydraulically fracture stimulated well at Senecio could be economically viable," Clement noted in a statement.

"The Perth Basin is potentially a very important source of energy for the Western Australian market and we believe that the timely completion of a development feasibility study will help define a valuable gas resource," Clement added.

AWE plans to consider the use of nearby existing plant processing infrastructure to minimize the project's environmental footprint and development costs. Evaluation of the Dongara and Xyris gas plants and associated infrastructure will form part of the study.
Detailed work on project planning, budget and product marketing may start as soon as 2Q 2013.

Clement said: "The unconventional gas program in the Perth Basin has been very successful to date, significantly increasing our understanding of the geological and commercial potential of the tight gas and shale gas opportunities in the Basin.

Our exploration team is looking at 30 years of accumulated data for the Perth Basin, compiled through conventional oil and gas exploration activities, to identify additional tight gas intersections with development potential."

Generated by readers, the comments included herein do not reflect the views and opinions of Rigzone. All comments are subject to editorial review. Off-topic, inappropriate or insulting comments will be removed.

View the original article here

SKKMigas: Pipeline Leak Resolved, Chevron Resumes Oil Deliveries from Riau

Oil deliveries from Chevron Corp’s fields in Indonesia's Riau province have resumed, following delays early this week due to a pipeline leak, SKKMigas disclosed in a statement late Thursday.

A breach of the 47-mile (76-kilometer) pipeline, which occurred Tuesday, disrupted deliveries of oil from the Bangko area to the Dumai terminal, SKKMigas' Deputy of Operations, Gde Pradnyana, said in a statement.

SKKMigas and Chevron Pacific Indonesia started repair and clean-up works Wednesday, with operations expected to return to normal Friday. SKKMigas was not reachable for an update on the repair and clean-up operations Friday. 

Seven workers were exposed to splashes of oil. Three workers were flown by helicopter to a nearby hospital Tuesday, while the remaining four were sent back home as their "conditions were not alarming." Of the three hospitalized workers, two are already discharged Thursday.

SKKMigas and Chevron Pacific Indonesia are at present conducting a joint investigation to confirm the cause of the accident and the volume of oil which spilled as a result.

The pipeline delivers output from the Duri field in the Rokan production sharing contract (PSC).

The Duri field is the largest producing field operated by Chevron in Indonesia. The field, discovered in 1941 on the island of Sumatra, is home to one of the world’s largest steamflood projects. Extensions to the field are on-going at present.

Quintella has reported on the upstream and downstream oil and petrochemicals markets from 2004. Email Quintella at quintella.koh@rigzone.com.

Generated by readers, the comments included herein do not reflect the views and opinions of Rigzone. All comments are subject to editorial review. Off-topic, inappropriate or insulting comments will be removed.

View the original article here

Man Working at Carroll Site Crushes Hand

A worker on the Harvey oil-well site on Buttercup Road in Washington Township was injured Tuesday morning when his hand became caught in the main controls for the rig.

Carroll County Sheriff Dale Williams said his office received the call for assistance at 11:22 a.m. and his deputies responded, as well as Fox Township, Carroll County and Carrollton Village fire departments.

Williams said the man's hand was crushed and a piece of metal impaled his hand.

Williams said the injuries were not life-threatening and the main was transported by ambulance to a Canton hospital.

Copyright 2013 The Times Reporter Distributed by Newsbank, Inc. All Rights Reserved

Generated by readers, the comments included herein do not reflect the views and opinions of Rigzone. All comments are subject to editorial review. Off-topic, inappropriate or insulting comments will be removed.

View the original article here

Gunmen Blow Up Marib Oil Pipeline in Yemen

SAN'A, Yemen - Gunmen in Yemen Friday blew up a key oil pipeline that has been repeatedly attacked in the country's eastern Marib province, a security official and witnesses said.

"Subversive elements in Wadi Obaida (around 12 kilometers from Marib) blew up" the 320-kilometre pipeline that carries oil from the Safer oilfields in Marib to an export terminal on the Red Sea, the official said.

Witnesses said flames erupted from the pipeline that carries around 180,000 barrels a day following the explosion early Friday.

Attacks on oil and gas pipelines by al Qaeda or by tribesmen seeking to win concessions from the central government are common in Yemen, an impoverished country that produces about 300,000 barrels of oil a day, mostly for export.

In December, the army launched an offensive against tribesmen suspected of repeatedly sabotaging the pipeline, sparking clashes which left 17 people dead.

According to official figures, lost production because of pipeline attacks in the east cost the government more than $1 billion in 2012, while oil exports fell by 4.5%.

In July, Petroleum and Minerals Minister Hisham Abdullah said Yemen had lost more than $4 billion in revenues since February 2011 because of such attacks.

Copyright (c) 2012 Dow Jones & Company, Inc.

Generated by readers, the comments included herein do not reflect the views and opinions of Rigzone. All comments are subject to editorial review. Off-topic, inappropriate or insulting comments will be removed.

View the original article here